The reconstruction of on-shore pumping station combined with a water inlet without a stop of work of Chelyabinsk metallurgical plant

Бесплатный доступ

The plan of reconstruction of an on-shore pumping station combined with a water inlet of Chelyabinsk Metallurgical Plant (CMP) is developed. The authors give characteristics of the quality and amount of water, needed for the main production of CMP. The inspection of the on-shore pumping station combined with the water inlet of CMP is carried out. The need for reconstruction for reliability control and compliance with modern requirements of water intake of an industrial enterprise, which in turn is connected with the expansion of production at CMP is proven. The basic equipment is specified. It leads to the enlargement of the pumping station itself.

Еще

Pumping station, water inlet, main production, chelyabinsk metallurgical plant, pumps, quality and amount of service water

Короткий адрес: https://sciup.org/147154468

IDR: 147154468   |   DOI: 10.14529/build160409

Статья научная