Monitoring of the construction site using an information model

Автор: Grishina Olga, Savchenko Alexey, Marichev Alexey, Zalata Ekaterina, Petrochenko Marina

Журнал: Строительство уникальных зданий и сооружений @unistroy

Статья в выпуске: 12 (63), 2017 года.

Бесплатный доступ

BIM technologies are an integral part of the modern building process. In order to approach the complex implementation of BIM, it is necessary to use not only the 3D modeling process. The next step is to generate a 4D model based on the 3D model and work schedule. Russian construction companies implementing BIM are beginning to implement 4D models not only during the design phase but also during the construction phase. This article shows the principle of control of the construction site due to the information model. The most common software applications are identified. Their main characteristics are clarified and also in what situations the software applications can be used to organize the most effective work.

Еще

Information model, 4d bim, 4d modeling, 4d bim tools, work schedule

Короткий адрес: https://sciup.org/143163576

IDR: 143163576   |   DOI: 10.18720/CUBS.62.1

Список литературы Monitoring of the construction site using an information model

  • Strategiya innovatsionnogo razvitiya Rossiyskoy Federatsii na period do 2020 goda (utverzhdena rasporyazheniyem Pravitelstva Rossiyskoy Federatsii ot 8 dekabrya 2011 g. №2227-r «Ob utverzhdenii Strategii innovatsionnogo razvitiya Rossiyskoy Federatsii na period do 2020 goda»).
  • Protokol zasedaniya Pravitelstvennoy komissii po vysokim tekhnologiyam i innovatsiyam ot 3 avgusta 2010 g. №4.
  • Metodicheskiye materialy po razrabotke programm innovatsionnogo razvitiya aktsionernykh obshchestv s gosudarstvennym uchastiyem, gosudarstvennykh korporatsiy i federalnykh gosudarstvennykh unitarnykh predpriyatiy (utverzhdeny rasporyazheniyem Minekonomrazvitiya Rossii ot 31 yanvarya 2011 g. №3R-OF).
  • Metodicheskiye materialy po razrabotke pasportov programm innovatsionnogo razvitiya aktsionernykh obshchestv s gosudarstvennym uchastiyem, gosudarstvennykh korporatsiy i federalnykh gosudarstvennykh unitarnykh predpriyatiy (odobreny resheniyem Rabochey gruppy po razvitiyu chastno-gosudarstvennogo partnerstva v innovatsionnoy sfere pri Pravitelstvennoy komissii po vysokim tekhnologiyam i innovatsiyam ot 15 noyabrya 2011 g., protokol №43-AK).
  • Chetverik N. P. Otsenka effektivnosti innovatsiy na etape proyekta//Nauka i bezopasnost. 2014. No. 2(11). Pp. 2-33.
  • Jacobi J. 4D BIM or Simulation-Based Modeling. Structure Magazine. 2011. Pp. 17-18. Nomer zhurnala. Строительство уникальных зданий и сооружений, 2017, №12 (63) Construction of Unique Buildings and Structures, 2017, №12 (63) 16 Reich E.V., M. Lima, Strelets K.I. Efficiency of applying sustainable technology of bubbledeck technology in concrete in Russia/Рейх Е.В., Лима М., Стрелец К.И. Эффективность применения экологически устойчивой технологии пустотных бетонных плит с пластиковым заполнителем в России ©
  • Liao, Y. F., Hsieh, S. H., Kang, S. C., Chen, C. S., Yang, C. T., Chi, H. L., Chi, W. C. and Yu, C. H. Development and application of 4D construction simulation tools. Proceedings of The Fourth Civil Engineering Conference in the Asian Region (CECAR), 2007.
  • Singh, V., Gu, N. and Wang, X. A Theoretical Framework of a BIM-Based Multi-Disciplinary Collaboration Platform. Automation in Construction. 2011. No. 20. Pp. 134-144.
  • Alcínia Zita Sampaio. BIM as a Computer-Aided Design Methodology in Civil Engineering. Journal of Software Engineering and Applications. 2017. No. 10. Pp. 194-210.
  • Marko Paavela, Kristo Karjusta, Jüri Majaka. PLM Maturity model development and implementation in SME. Procedia CIRP. 2017. No. 63. Pp. 651-657.
  • Wang, X. Extending Building Information Modelling (BIM): A Review of the BIM Handbook. Australasian Journal of Construction Economics and Building. 2012. No. 12. Pp. 101-102.
  • Nesterov I.V. Informatsionnoye modelirovaniye v stroitelstve. SAPR i GIS avtomobilnykh dorog. 2014. No. 2(3). Pp. 33-36.
  • Douglas M. Brito, Emerson A. M. Ferreira. Strategies for representation and analyses of 4D modeling applied to construction project management. Procedia Economics and Finance. 2015. No. 21. Pp. 374-382.
  • Sheryl Staub-French, Atul Khanzode. 3D and 4D modeling for design and construction coordination: issues and lessons learned. ITcon. 2007. Vol. 12. Pp. 381-407.
  • Yashchenko A.A. Primeneniye 4D modelirovaniya v kalendarnom planirovanii na baze tekhnologicheskoy platformy BIM. Sbornik trudov Vosemnadtsatoy Mezhdunarodnoy mezhvuzovskoy nauchno-prakticheskoy konferentsii studentov, magistrantov, aspirantov i molodykh uchenykh. Stroitelstvo -formirovaniye sredy zhiznedeyatelnosti. Moskva, 2015. Pp. 715-718.
  • Eastman C., Teicholz P., et al. BIM Handbook: A Guide to Building Information Modeling for Owners, Managers, Designers, Engineers and Contractors. Hoboken, New Jersey, Wiley, 2011. 490 p.
  • Eadie, R., Browne, M., Odeyinka, H., McKeown, C., McNiff, S. BIM Implementation throughout the UK Construction Project Lifecycle: An Analysis. 2013. Automation in Construction. No. 36. Pp. 145-151.
  • Eastman C., Fisher D., Lafue G., et al. An Outline of the Building Description System. Institute of Physical Planning, Carnegie-Mellon University, 1974. 23 p.
  • Azhar, S., Hein, M. and Sketo, B. Building Information Modeling (BIM): Trends, Benefits, Risks, and Challenges for the AEC Industry. Leadership Manage. Eng. 2011. No. 11(3). Pp. 241-252.
  • Tardif, M. and Smith K.D. Building Information Modeling: A Strategic Implementation Guide. John Wiley & Sons, Hoboken. 2009. 216 p.
  • Azhar, S et al. Building information modeling (BIM): now and beyond. Australasian Journal of Construction Economics and Building. 2012. No. 12 (4). Pp. 15-28.
  • B. Koo, M. Fischer, Feasibility study of 4D CAD in commercial construction. Journal of const. Eng. & Manage. 2000. No. 126 (4). Pp. 251-260.
  • Olde Scholtenhuis, L., Hartmann, T., and Dorée, A. Comparing Mindfulness in Manual and 4D-Supported Coordination Practices. In: Proceedings of Construction Research Congress. Atlanta, USA, 2014. Pp. 160-168.
  • Hsieh, S.H., Chen, C.S., Liao, Y.F., Yang, C. T. and Wu, I.C. Construction director: 4D simulation system for plant construction. Proceedings of the 10th East Asia-Pacific Conference on Structural Engineering and Construction (EASEC-10). Bangkok, Thailand, 2006.
  • Tsai, M. H., Kang, S. C., Hsieh, S. H., Kuo, C. H., Pei, T. J. and Yeh, K. C. Experiences on study of setting-up a 4D construction management tool in a high-rise construction project. Proceedings of 12th International Conferences on Computing in Civil and Building Engineering & 2008 International Conference on Information Technology in Construction (ICCCBE XII & INCITE 2008). Beijing, China, 2008.
  • Dawood, N., and Mallasi, Z. Construction Workplace Planning: Assignment and Analysis Utilizing 4D Visualization Technologies. Computer-aided Civil and Infrastructure Engineering. 2006. Vol. 21, Is. 7. Pp. 498-513.
  • PAS 1192-2:2013: Specification for information management for the capital/delivery phase of construction projects using building information modeling (BIM). BSI, UK. 2013.
Еще
Статья научная